B.N. Duke Auditorium
Construction
Year: 1937
Gross Area: 13,491 sq. ft.
Construction Cost: $85,000
Last Renovation: 1990
Last Renovation Cost: $845,000
Renovation and Expansion
Budget -- $2.8 million
Upgrade lighting system
Replace carpet
Repair roof
Expand music classroom
Add bathrooms
Add recording studio
Upgrade HVAC system
Completion Date: September 2003
(Completion dates are subject to change).
Update
Construction contract awarded in Oct 2002
Jordan House has been demolished
Completion in June 2003
Auditorium needed for University activities in August 2003
|